Project C2075 ATLAS COPCO HTL2
Project Manager Paul Coogan
Client Atlas Copco Ltd
Location Deeside , CH5 2NX
Duration 20 Weeks; commencing on site October 2018

Relocation of Heat Treatment Line No. 2

We are continuing to make progress on site with the relocation and upgrade of the Heat Treatment line no. 2.

The line is moving from the older facility over to the newly refurbished facility on Parkway One.

The work is due for completion in April 2019.

Control Panel tray drops to low level for rear entry

The works are being installed in conjunction with Atlas Copco and Kohne and have included the decommissioning of the existing Line 02, Installation of new supply cables, new infrastructure of containment and cabling, connection of control cabling, testing and commissioning.

Trays will be lidded throughout upon completion.

 