Job Centre Plus Boiler room modifications

Job Centre Plus boiler house replacement works 

About the client

Job Centre Plus boiler house replacement works

The project was carried out by Gilks mechanical team between November 2020 & March 2021

The project involved replacement of boiler plant, pumps, dosing pots, flues and air dirt separators with upgrades to the existing gas system and BMS control panels in seven job centres throughout the east & west midlands.

The job centres were occupied during the works and temporary heating to the buildings was installed to prevent disruption to the daily operation of the offices.

On completion all plant was tested & commissioned , thermally insulated and the existing systems were chemically flushed and inhibitor added.

The project was carried out by Gilks mechanical team between November 2020 & March 2021

The project involved replacement of boiler plant, pumps, dosing pots, flues and air dirt separators with upgrades to the existing gas system and BMS control panels in seven job centres throughout the east & west midlands.

The job centres were occupied during the works and temporary heating to the buildings was installed to prevent disruption to the daily operation of the offices.

On completion all plant was tested & commissioned , thermally insulated and the existing systems were chemically flushed and inhibitor added.

Project: Job Centre Plus Boiler room modifications

Client: Seddon Construction ltd
Location: Midlands
Duration: 26 weeks

 

The project incorporated the following services within the scheme:

  • Full project management
  • Replacement Boilers
  • Replacement Flues
  • Replacement Pumps
  • Replacement Dosing pots
  • Replacement Gas safety systems
  • New Air/Dirt separators installed
  • Thermal insulation
  • BMS upgrade to existing controls & MCP
  • LTHW heating flushed & inhibitor added
  • Testing and commissioning

Related Case Studies

8th Oct, 2021
New 350A Process Supply

The project involved installing ladder containment systems externally, and building a purpose made bridge to facilitate the new containment/cabling...

Read more
17th May, 2023
NSCG – Newcastle and Stafford Colleges Group

Improving the environment and providing energy efficiencies.

Read more
8th Oct, 2021
Tattenhall Care Village – Phase 2

The project was the second phase of a continuing care retirement community (CCRC) at Tattenhall, Chester, which included 56...

Read more