Date: 15 Oct 2021

Jones Brothers - Phase 2 - VRF Air Conditioning Installation

The project, carried out at Jones Brothers Civil Engineering UK, in Ruthin, North Wales, was carried out by Gilks’ Mechanical Team between February and July 2020.

We were required to decommission the existing wet heating system and replace it with a new VRF Air Conditioning System for the office areas and electric panel heaters in the toilet and circulation areas.

A purpose made condenser compound was formed to the east elevation of the building with the VRF services running through the existing ceiling voids to serve ceiling mounted cassettes in various locations throughout.

The project was carried out in four phases to reduce any disruption to the daily operations of the client’s business. Gilks carried out the role as the main contractor for this particular project which was completed on time and to budget.

The project incorporate the following services :

  • Full Project-Management
  • Associated Electrical Installation
  • Electrical Panel Heaters
  • General Building work
  • VRF Condenser Compound
  • Palisade Fencing
  • Existing heating removal
  • VRF Installation
  • Testing & Commissioning

Related Case Studies

14th Oct, 2021
Eastbourne Care Home

Our brief was to design, supply and install the electrical services to the new development, utilising the latest in...

Read more
12th Oct, 2022
Castle Donnington Primary School

Gilks was responsible for the design and installation of the electrical systems internally and externally. Due to one side of...

Read more
20th Dec, 2022
Wythenshawe College

The project involved the refurbishment and change of use of teaching spaces in various areas of the College including...

Read more